Inside the eight-day job to resurface the A4169 from Shifnal to The Hem

Shropshire Council will resurface the A4169 from Shifnal to The Hem, including the Bridgnorth Road roundabout, with an A4169 road closure from 9.30am to 4pm on weekdays, 19–28 October.

The A4169 between Shifnal and The Hem will close to through traffic for eight working days this month, and the work will happen in daylight.
Shropshire Council will resurface the road from Monday 19 to Wednesday 28 October 2026. The work includes the Bridgnorth Road roundabout and its approaches, with a full closure from 9.30am to 4pm on weekdays only.
In brief:
- The A4169 will be resurfaced from Shifnal to The Hem, including the Bridgnorth Road roundabout and its approaches.
- The road will close fully from 9.30am to 4pm on weekdays, 19–28 October 2026.
- Shropshire Council says resurfacing will improve long-term road condition and reduce the need for pothole repairs.
- Other traffic will follow a signed diversion. Residents, businesses, pedestrians and emergency vehicles keep access.
What the A4169 road closure involves
Outside the working hours, the road reopens. Each morning the closure goes back up at 9.30am, and each afternoon it comes down at 4pm. That timing avoids both rush hours, which matters on a route linking Shifnal with the wider road network to the south.
While the road is closed, the council says residents and businesses within the closure will keep access when it’s safe. Pedestrians, dismounted cyclists, horse riders and emergency vehicles on blue lights can also get through. Everyone else follows a signed diversion. As with other Shropshire schemes, some drivers may be able to choose a different diversion depending on their vehicle. The council is also asking people not to park on the road while the works are under way.
Resurfacing is not the same as patching or surface dressing. Patching fixes individual defects. Surface dressing seals the existing surface with a binder and chippings. Resurfacing removes the worn top layer of the road, usually by planing it off, and lays new asphalt in its place. It’s the right treatment when a stretch has deteriorated too far for spot repairs to make sense. The council says the aim is to improve long-term road condition, prevent further structural problems and reduce the need for smaller repairs such as filling potholes.
The roundabout is the awkward part. Roundabouts take more punishment than straight sections of road. Vehicles brake on the approach, turn under load and accelerate away, and that steady shearing wears the surface faster. They’re also hard to resurface in stages with traffic still running, because every arm feeds into the same circle. Closing the whole thing lets the surfacing crew work across the full width in long, continuous runs. That usually means fewer joints, and joints are where a new surface tends to fail first.
The council hasn’t said why it chose daytime working, though it does have practical advantages in October. Asphalt needs to stay hot enough to compact properly, and longer daylight and warmer daytime temperatures help with that. The alternative to a full closure would be a lane at a time under temporary lights. Anyone who has queued at a run of temporary lights will know how quickly that becomes the bigger problem. We looked at that effect recently in Oxfordshire’s overlapping roadworks schemes, where the timing and layout of the works became the story.
For drivers, the practical advice is simple: between 9.30am and 4pm on weekdays from 19 October, plan for the diversion and don’t count on getting through. For residents along the route, access stays open but expect delays near the work area. The council lists the works on the One Network roadworks website, which shows the latest closure details.
If the programme holds, the road will reopen fully after 4pm on Wednesday 28 October with a new surface.