A5 dual carriageway work on over 300 landowners’ land waits for 2027

A Court of Appeal ruling on 6 October cleared the way for the A5 dual carriageway scheme, and the Department for Infrastructure has now updated landowners on compensation and timing.

Major construction on land to be vested for the A5 dual carriageway won’t start until after 31 December 2026, the Department for Infrastructure says, as it waits for the Court of Appeal’s formal order. The update covers more than 300 landowners affected by the first phase, Section 2 and Section 3 Phase 1B, between south of Strabane and Ballygawley. Before then, any necessary activity on the land is limited to surveys and other essential preparatory work.
In brief:
- Claims arising from evidenced financial impacts will be assessed independently by Land & Property Services, case by case
- The department meets reasonable professional fees for the agents representing landowners
- It is still waiting for the formal order giving effect to the Court of Appeal judgment of 6 October 2026
A5 dual carriageway land and compensation after the court ruling
The department says the legal proceedings and the quashing of the vesting orders disrupted the normal compensation process and delayed access to compensation funding for some affected landowners. Since the High Court judgment in June 2025, every affected landowner has been offered an individual meeting with the project team, and officials meet the Ulster Farmers’ Union regularly, including at senior official level. Infrastructure Minister Liz Kimmins has committed that major construction won’t begin on any of the lands until after 31 December 2026.
It recognises “the uncertainty that landowners, their families and businesses affected by the A5 Western Transport Corridor have faced over a prolonged period”, and has set up a questions and answers page for landowners. That page says it would be premature to give a firm construction date until it is clearer whether any party will seek leave to appeal.
The Court of Appeal in Belfast overturned the High Court’s ruling on all grounds, ITV News reported. The appeal covered environmental impact assessment, human rights and compliance with climate change legislation, and the Lady Chief Justice, Dame Siobhan Keegan, called the litigation history “long and tortuous”.
The department’s Q&A page also says the £1.7bn figure reported in the media isn’t its latest published estimate and that the emerging cost of the 55km Phase 1B section was about £1.2bn in October 2024, with estimates now under review. It puts spend on the project to 2025/26 at £192.5m and says the land has not yet reverted to the Department, which is expected once the court makes its formal order.
The scheme would provide 85 kilometres of new road from New Buildings to the border at Aughnacloy, 82km of it dual carriageway, and contractors have been appointed for each of its three sections. The department’s notes say it has faced three public inquiries and four legal challenges. The release doesn’t give a date for the formal court order or for the start of construction. The department also updated Mid and East Antrim councillors on its road maintenance plans this month, as we reported.
Source: Department for Infrastructure, published 26 October 2026