A55 North Wales Expressway: who runs it, and the 2028 handover

Our guide to the A55 North Wales Expressway covers who owns and runs it, the tunnels and bridges that define it, and the work under way from Holyhead to the English border.

The A55 has one owner but two operators, and one of them hands back in 2028.
The Welsh Government owns the road and makes the decisions. Most of it is run day to day by a public trunk road agent, but the Anglesey end has been in private hands since 1998, under a 30-year contract.
In brief:
- The Welsh Ministers are the highway authority, and the North and Mid Wales Trunk Road Agent manages most of the road for them.
- A private operator runs junctions 1 to 11 until 2028, when the work passes back to the Welsh Government.
- Development work on a third Menai crossing restarted in October 2026, three years after the scheme was dropped.
Who runs the A55 North Wales Expressway and what is changing
Who is responsible. The A55 North Wales Expressway is a trunk road, so the Welsh Ministers are its highway authority. It runs from Holyhead on Anglesey, across the Menai Strait and along the coast to the border with England near Chester, with junctions numbered eastwards from junction 1 at Holyhead. Day-to-day management sits with the North and Mid Wales Trunk Road Agent (NMWTRA), which manages and maintains about 1,080km (670 miles) of trunk road across north and mid Wales for the Welsh Government, including three A55 tunnels. Tarmac, one of our partners, won a place on NMWTRA’s maintenance framework in 2025. More on Tarmac’s framework win.
The private section. In December 1998, a 30-year design, build, finance and operate contract was awarded to UK Highways A55 DBFO Ltd, the first privately financed road in Wales. The company operates and maintains the A55 from junction 1 to junction 11, plus the A5 Menai loop, which includes the Menai Suspension Bridge. The Welsh Government pays it a “shadow toll” based on traffic using the road. The contract is due to end in 2028, when the section returns to public management.
Tunnels and bridges. Conwy Tunnel takes the road under the Conwy estuary between junctions 17 and 18. It was opened by the Queen on 25 October 1991, and was Britain’s first immersed-tube road tunnel. Further west, Britannia Bridge carries the road over the Menai Strait to Anglesey.
Work in the tunnels. A vehicle fire in the westbound bore of Conwy Tunnel on 19 June 2025 closed the tunnel in both directions, and one bore partially reopened the next morning with a contraflow. The westbound bore then closed from 10 to 20 January 2026 for new LED lighting, safety barriers and walkway repairs. The Welsh Government said this was routine wear-and-tear work, not connected to the fire.
Resurfacing. The eastbound carriageway between junction 34 (Ewloe) and junction 35 (Dobshill) closed for four weeks from 22 February 2026. Crews removed worn surfacing, repaired the concrete slabs underneath, replaced gullies and manholes, and resurfaced. The work was part of an extra £25m from the Welsh Government for potholes on the strategic road network.
The Menai Strait. In November 2025, the Welsh Government said it would spend more than £1m over two to three years on wind deflectors for Britannia Bridge, together with variable speed limits and upgraded traffic management equipment. On 6 October 2026, Deputy Minister for Transport Mark Hooper announced the immediate restart of development work on a third Menai crossing, covering design, environmental assessment, the business case and statutory approvals. A three-lane tidal-flow scheme on Britannia Bridge was ruled out over safety and operational concerns.
Schemes dropped in 2023. The Welsh Government’s response to its Roads Review halted the third Menai crossing, the Flintshire Corridor and the A483 Wrexham bypass junctions 3 to 6. The Flintshire Corridor, also known as the Red Route, would have been a 13km dual carriageway in north-east Wales, estimated in 2019 at £300m. The review panel described it as “unsustainable, unjustifiable and damaging”.
Current and recent schemes at a glance:
- Conwy Tunnel safety works, junctions 17–18 westbound: done January 2026, cost not published
- Ewloe to Dobshill resurfacing, junctions 34–35 eastbound: done February to March 2026, part of £25m
- Britannia Bridge wind deflectors and variable speed limits: in development, over £1m
- Third Menai crossing: restarted October 2026, cost not published
- Flintshire Corridor: halted 2023, £300m (2019 estimate)
- UK Highways A55 contract, junctions 1–11: ends 2028
The Welsh Government hasn’t published costs for the Conwy Tunnel works or the third Menai crossing.
Source: Welsh Government, written statements and announcements, November 2025 to 6 October 2026; Traffic Wales; Royal Commission on the Ancient and Historical Monuments of Wales