A66 closures at Penrith start 12 October, with four weekends to follow

National Highways is closing the A66 overnight at Penrith from 12 October, followed by lane closures on four weekends. Here are the A66 closures at Penrith and what the work involves.

Overnight closures of the A66 at Penrith start on 12 October, followed by four consecutive weekends of lane closures. National Highways says the work is part of its A66 Northern Trans-Pennine project, and that vegetation clearance across the project will continue until 30 November 2026.
In brief:
- Overnight closures run in both directions from midnight to 6am on 12 to 14 October, between Kemplay Bank roundabout and Temple Sowerby
- Weekend lane closures in both directions run on 16–19 October, 23–26 October, 30 October–2 November and 6–9 November, from 7pm on Friday until 6am on Monday, between Kemplay Bank roundabout and Brougham
- The work covers vegetation clearance, strengthening the central reservation and installing new drainage
A66 closures at Penrith: the dates and the work
The overnight closures on 12 to 14 October apply in both directions between the Kemplay Bank roundabout and Temple Sowerby. The weekend lane closures that follow are between the Kemplay Bank roundabout and Brougham and run from 7pm on Friday until 6am on Monday. National Highways’ latest updates page carries a diversion map for the overnight closures.
One restriction is already in. The westbound carriageway between the Brougham and Kemplay Bank roundabouts has been reduced to one lane so that work on the central reservation and drainage can take place. The work follows similar upgrades completed between M6 junction 40 and Kemplay Bank roundabout earlier this year.
None of the three jobs is the dualling itself. Clearing vegetation, strengthening the central reservation and laying drainage are typically the kind of enabling work done ahead of heavier construction beside live traffic. That’s general practice, not a description National Highways has given of this phase.
National Highways describes the wider scheme as improving the A66 between the M6 at Penrith and the A1(M) at Scotch Corner, upgrading single carriageway sections to dual carriageway standard and improving junctions along the route. Its development consent order, the planning permission for nationally significant infrastructure, was approved on 7 March 2024. In May we reported on a community woodland refreshed as a legacy of the A66 dualling project. We’ve previously reported on Cumbria’s roadworks squeeze on the M6 and A66.
For drivers, the dates to note are the early hours of 12 to 14 October and every weekend from 16 October to 9 November.
In this story National Highways