A69 Warwick Road in Carlisle to be resurfaced in the evenings

Cumberland Council’s A69 Warwick Road resurfacing in Carlisle starts on Sunday 18 October, with evening signals at the Tesco junction, then five nights of 7pm to 1am closures and signed diversions.

Cumberland Council is resurfacing the A69 Warwick Road in Carlisle in the evening and overnight, when traffic is lighter, to keep disruption to daytime traffic, residents and businesses down.
The work runs between the Tesco junction and Tilbury Road and is due to start on Sunday 18 October 2026, subject to weather and site conditions.
In brief:
- Phase 1, from Sunday 18 October: four-way temporary traffic signals at the Tesco junction from 4.30pm to 1am.
- Phase 2, Monday 19 to Friday 23 October: evening road closures from 7pm to 1am between Montgomery Way and Tilbury Road.
- HGVs will be diverted via the M6 and A6 London Road, and local traffic via Montgomery Way and Durranhill Road.
How the A69 Warwick Road resurfacing is phased
The council is splitting the scheme into two phases so the resurfacing can be carried out safely and efficiently. Phase 1 starts on Sunday 18 October at the Tesco junction, where four-way temporary traffic signals will be in place from 4.30pm to 1am while the work is done.
From Monday 19 to Friday 23 October, the work moves to the section between Montgomery Way and Tilbury Road. That stretch will be closed from 7pm to 1am each night, with a signed diversion. HGVs will be sent via the M6 and A6 London Road, and local traffic via Montgomery Way and Durranhill Road.
The closing time isn’t the end of the night’s work. The council says it will aim to remove the traffic management by 3am each morning, leaving time for site clearance and for the newly laid material to cure before the road reopens. Resurfacing replaces a worn layer of the carriageway instead of patching individual defects, so the fresh surface needs that time before traffic runs on it.
Access for emergency vehicles, pedestrians and dismounted cyclists will be maintained throughout. Access to the Toby Carvery will also be maintained and clearly signed, and residents inside the works area who need access are asked to speak to site staff.
The council says the job is part of its ongoing programme of highway maintenance, aimed at improving road conditions and extending the life of the carriageway. Our coverage of Cumberland’s highways investment plan sets out the council’s wider spending on its roads.
Updates are available from the Highways Hotline on 0300 373 3736, and live and planned roadworks can be checked on one.network.
Evening drivers, HGV operators and residents in the works area are the ones who need to plan around the week of 19 October.