A9 Allan Water Bridge gets £1m refurbishment from 6 November

Amey will carry out a £1m refurbishment of the A9 Allan Water Bridge near Dunblane for Transport Scotland in two phases until February, with a 24-hour contraflow carrying one lane each way.

The work covers carriageway and footway resurfacing, waterproofing, replacement of the bridge expansion joints, kerb and drainage improvements and concrete repairs. More than 29,400 road users use the route each day, according to Traffic Scotland.
In brief:
- The northbound carriageway closes from Monday 9 November until Monday 14 December 2026, with traffic in the contraflow
- Traffic management comes off over the festive period, and the contraflow returns from Friday 8 January 2027
- The southbound side is then refurbished until Thursday 18 February 2027
A9 Allan Water Bridge closures and contraflow dates
Amey is carrying out the £1 million refurbishment on behalf of Transport Scotland in two phases, between Friday 6 November 2026 and Sunday 21 February 2027. A 24-hour contraflow will be in place during each phase, with traffic in a single lane in each direction across the bridge.
Overnight lane closures from 7.30pm to 6.30am will set up and stand down the contraflow between Friday 6 and Monday 9 November 2026, Monday 14 and Thursday 17 December 2026, Tuesday 5 and Friday 8 January 2027, and Thursday 18 and Sunday 21 February 2027. Amey says it will do the noisiest work during the day, and all schemes are weather dependent and may be cancelled or rescheduled. Amey’s trunk roads website carries full information on roadworks in the north-east of Scotland.
The refurbishment follows Amey’s overnight structural investigations on the bridge in June 2026, which were needed to understand its condition before any deck refurbishment. In August, Amey resurfaced about 1,120 metres of the southbound A9 between Allan Water and Stockbridge in a £324,000 project. Further north, BEAR Scotland’s A9 safety barrier works at Dalnaspidal started on 19 October and are expected to last up to four weeks.
Source: A9 at Allan Water Bridge, Essential Maintenance, Traffic Scotland, works from 6 November 2026