A9 Pitlochry to Killiecrankie dualling moves closer with £220m deal

The Scottish Government intends to award Wills Bros a £220m contract for the A9 Pitlochry to Killiecrankie dualling, the fifth section of the programme to move to construction.

The next section of A9 dualling has a preferred contractor.
Cabinet Secretary for Economy, Tourism and Transport Stephen Flynn has announced his intention to award Wills Bros Civil Engineering Ltd the £220.02m construction contract to dual the A9 between Pitlochry and Killiecrankie.
In brief:
- The contract will be formally awarded after a mandatory standstill period, the final stage of procurement.
- The 6.4km scheme includes two grade-separated junctions, a new crossing of the River Tummel and a new rail bridge over the Highland Main Line.
- The section will help take the A9 between Perth and Inverness to 50% dual carriageway by 2030.
What the A9 Pitlochry to Killiecrankie dualling involves
The scheme dualls about four miles (6.4km) of single carriageway: roughly 4km of widening along the existing road and 2km of new offline construction. It includes two grade-separated junctions and two left-in, left-out junctions. There will be two major underbridges, including a new crossing of the River Tummel alongside the existing Tummel Bridge and a new bridge alongside Clunie Bridge over Loch Faskally. Three existing underbridges will be demolished and replaced, one rail underbridge extended and a new one built over the Highland Main Line, plus five more underbridges or underpasses, six retaining walls and 15 culverts. The project also includes active travel routes and flood mitigation measures.
The Scottish Government says the contract is expected to create 60 full-time equivalent jobs, including local and regional opportunities, as well as 17 graduate roles, 11 apprenticeships and eight new-entrant positions. It expects around £33m of opportunities for small and medium-sized businesses and suppliers near the site. The contractor’s social value commitments include £350,000 of investment, 300 hours of volunteering for local community projects and 300 hours of school and STEM engagement.
Flynn said: “This contract award marks another significant milestone in the Scottish Government’s £3.97 billion investment to dual the A9. This is an investment in Scotland’s future. Alongside delivering a safer and more resilient A9, this contract will create jobs, develop skills, provide opportunities for local businesses and invest directly in the communities it serves.”
Advance works are already under way to prepare the site, including archaeological investigations, tree felling and the demolition of vacant properties. Once the contract is awarded, Wills Bros will begin mobilisation and detailed planning, including a series of “Meet the Contractor” events for local communities. Transport Scotland says it will keep residents and road users informed about traffic management.
The section is due to be operational by the end of 2030. Under the 2026 Delivery Plan, half the A9 between Perth and Inverness will be dualled by then, rising to 100% by the end of 2035. We reported in 2024 on the £185m contract for another section of the programme.
Source: Transport Scotland press release, issued 22 October 2026