The 60-year-old motorway junction being rebuilt in two halves this winter

The Almondsbury Interchange closure shuts the link from the M4 westbound to the M5 northbound until early December, the first phase of £4.5m of permanent repairs following emergency fixes in 2024.

The link from the M4 westbound to the M5 northbound at the Almondsbury Interchange closed at 10pm on Sunday 11 October, and it will stay shut around the clock until early December.
National Highways is carrying out £4.5m of permanent repairs at the 60-year-old junction, following temporary emergency fixes in 2024.
In brief:
- The M4 junction 20 westbound to M5 junction 15 northbound link is closed 24/7 until early December, with traffic diverted via M5 junction 16.
- A second phase, from mid-December to February 2027, closes the M4 eastbound to M5 southbound link, with a diversion via M5 junction 14.
- The £4.5m scheme makes permanent the temporary emergency repairs carried out at the junction in 2024.
What the Almondsbury Interchange closure is for
The work list covers lighting, camera installation, concrete repairs, waterproofing, the safety barrier, bridge joints, resurfacing, drainage, road markings and studs. Almondsbury opened to traffic in September 1966, so much of what’s being renewed has reached the end of a very long life.
Several of those jobs belong together. Bridge joints are the gaps that let a bridge deck expand and contract with temperature. Waterproofing sits beneath the road surface and keeps water out of the concrete below. Reaching either usually means lifting the surfacing first, which is one reason work like this is bundled into one long closure instead of many short ones. National Highways says its contractors are working two shifts a day, seven days a week.
The interchange connects the M4 and the M5 and serves Bristol, Aztec West, Cribbs Causeway and the Severn Bridges. During this first phase, traffic that would have used the closed link is sent south on the M5 to turn at junction 16. National Highways expects that diversion to add around four minutes off-peak. It also expects junction 16 to come under extra pressure and the M4 junction 22 to be busier than usual. Drivers can also use M48 junction 1 at Aust or M4 junction 22 at Pilning.
The second phase is the harder one. From mid-December to February, the M4 junction 20 eastbound to M5 junction 16 southbound link will close 24/7, with traffic diverted north via M5 junction 14. That diversion is expected to add around 15 minutes off-peak, and M4 junction 19 and M32 junction 1 are likely to be busier than usual.
A National Highways spokesperson asked drivers to consider avoiding the interchange at peak times, or to use alternative transport where possible for long-distance journeys. “We understand this work will be disruptive and have planned out work to ensure the repairs are completed as quickly and safely as possible,” the spokesperson said.
The reason for the disruption is the one National Highways gives itself: the work will prevent future emergency closures. The junction had to be patched up in an emergency in 2024, and this programme is the permanent fix.
National Highways hasn’t named the contractor. Bridge joints were also behind our recent report on M25 bridge repairs near Heathrow, where 40-year-old expansion joints are being replaced.
For drivers, the practical position until early December is a signed diversion in place of a direct turn from the M4 westbound to the M5 northbound. After that, it’s a longer diversion for traffic heading from the M4 eastbound to the M5 southbound.
In this story National Highways, Concrete Repairs Ltd