Four floods in 13 years: Aslackby’s £605,554 fix steers A15 water away from the village

Lincolnshire County Council has approved the £605,554 Aslackby drainage scheme near Bourne after homes flooded four times in 13 years. Water off the A15 will be steered away from the village.

Properties in Aslackby, near Bourne, have flooded four times in 13 years, including in 2024 and 2025.
Lincolnshire County Council has now approved a £605,554 drainage scheme around Temple Road, Aveland Way and Kirkby Underwood Road, aimed at a drainage system its own engineers describe as worn out and overloaded.
In brief:
- Engineers will repair and replace sections of pipework, improve parts of the existing network and add gullies to pick up surface water.
- Water coming off the A15 will be diverted away from the village drainage system.
- The money comes from the council’s 2026/27 Highways Asset Protection Drainage Budget.
What the Aslackby drainage scheme changes
David East, the council’s executive councillor for highways and transport, said engineers would repair and replace sections of pipework, improve parts of the existing network and put in extra gullies. A gully is the grated inlet at the roadside that takes rainwater off the carriageway and into the pipes below. More gullies means surface water leaves the road faster.
The investigation behind the scheme found large volumes of water coming straight off the A15 and escaping from the ditches alongside it. The council’s report described the village system as compromised both hydraulically and structurally, and found a section of pipe in Aslackby that had partially collapsed.
That’s why one of the biggest changes is to divert water running off the A15 away from the village drainage. East said this should take some of the pressure off the network and help reduce the likelihood of flooding in heavy rain. It’s a familiar principle in highway drainage. A village network has a fixed capacity, and every litre arriving from a main road is a litre the village pipes can’t use for their own streets. Separate the two, and more of that capacity is left for the homes it was built to protect.
Condition is the other reason for the work. East said engineers had found that some parts of the system had deteriorated, and some were reaching a point where they “could collapse” if repairs weren’t carried out. Nathan Whitfield, the council’s principal design engineer for drainage, told an earlier meeting that the existing system would keep deteriorating, increasing the risk of collapse and flooding. He also warned of a longer-term risk to the road: water escaping from failing pipes can create voids under the carriageway or soften its foundation.
There is an important caveat. Officials’ investigation found that the most likely cause of the flooding was the River Ave breaching its banks. The approved works focus on the highway drainage network and runoff from the A15, not the river itself. The scheme should stop the roads making matters worse and reduce the risk of the old pipes failing, but it can’t stop the river rising.
The decision was taken by East together with Thomas Catton, the executive councillor for resources. The report doesn’t give a start date, a programme length or a contractor, or say whether any of Temple Road, Aveland Way, Kirkby Underwood Road or the A15 will need to close while the work is done. Lincolnshire’s highways spending has been in front of councillors this autumn: in September we reported on a Lincolnshire scrutiny meeting on roads, transport and parking.
For residents of Aslackby, the real test will be the next spell of heavy rain, and whether the river stays within its banks.