Bakers Arms Roundabout drainage clean-up starts 1 November in Dorset

Dorset Council is clearing and jetting the drains around Bakers Arms Roundabout near Lytchett Minster before winter, a year after it enlarged the ditches at the flood-prone A35 and A350 junction.

Lane closures will be in place on the approaches to Bakers Arms Roundabout from Sunday 1 November to Monday 30 November, as Dorset Council carries out drainage maintenance to reduce the risk of flooding and disruption over the winter.
Drivers are being warned to expect delays.
In brief:
- Crews will inspect and assess the drainage network, remove debris and blockages, and cleanse and jet drains and pipework.
- Minor repairs found during the inspections, and clearance and maintenance of the ditches around the junction, are also in the programme.
- The works coincide with the temporary closure of the Sandbanks Chain Ferry, which the council says it took into account.
Why Bakers Arms Roundabout needs drainage work before winter
The roundabout connects the A35 and A350 and is one of the busiest routes in the area, the council says. It has flooded during periods of prolonged heavy rainfall in recent years, and in 2025 the council increased the capacity of the surrounding drainage ditches to improve the junction’s resilience to severe weather.
Cllr Jack Jeanes, Dorset Council cabinet member for place services, said: “The drainage improvements completed last year have significantly strengthened the site’s resilience. However, regular inspection and maintenance remain essential to ensure the network continues to operate effectively and that we maximise the benefit of those improvements.”
On the timing, he said: “We recognise these works coincide with the temporary closure of the Sandbanks Chain Ferry and have carefully considered the timing. However, completing this maintenance ahead of winter is important in helping to reduce the risk of flooding-related disruption later in the year.”
The work follows Dorset Council’s decision in February to set aside up to £5.25m for highway flood resilience, including a £5m fund for drainage hotspots and £250,000 for a dedicated gully crew, as listed in our guide to highways drainage schemes funded in 2026.
The release doesn’t give a cost, working hours or which approaches will be closed on which days.
Source: Dorset Council, published 29 October 2026