Banwell bypass opening slips to winter 2027 over water main works

North Somerset Council now expects the Banwell bypass to open in winter 2027 rather than summer 2027, because Bristol Water’s water main diversions must be finished before parts of the build can start.

The diversions move underground services out of the Banwell bypass construction area so that water supplies to local properties can be maintained and easily reached in future.
The bypass works include ground improvements such as piling, so the water main work has to come first. The council says it and contractor Galliford Try have rearranged programmes as far as possible to fit around it.
In brief:
- The council says the bypass will cut traffic through Banwell village by up to 78% in its opening year.
- Alun Griffiths Contractors Ltd pulled out in March 2024, and Galliford Try took over in September 2024.
- The council secured an extra £9.7m of government funding in March 2025.
Why the Banwell bypass is now due in winter 2027
Council leader Mike Bell said: “Banwell bypass is a project with a 100-year history, set to finally tackle notorious traffic congestion in the narrows of Banwell village. Despite delay we continue to make good progress on site and the century-long wait will soon be over.”
He added that the bypass will improve road links between Weston-super-Mare and the A38, and that the project includes miles of new walking, cycling and horse-riding track connecting with the Strawberry Line, along with new woodland, wetland and grassland.
The scheme has been a long time coming. According to the council’s project history, it secured Homes England funding in 2019 and planning permission in March 2023, and the Secretary of State for Transport confirmed the compulsory purchase orders in January 2024. Galliford Try’s contract runs in two stages, and Full Council agreed in April 2025 to go ahead with the second, main construction stage.
The release doesn’t give the scheme’s current cost, or whether the delay adds to it. Elsewhere, the DfT has dropped the £303m A350 Melksham bypass from its road funding programme.
Source: Utility delays on the Banwell bypass, North Somerset Council, published 2 November 2026
In this story Somerset Council, North Somerset Council, Griffiths (formerly Alun Griffiths Contractors)