Bicester strategic link road planning application due spring 2027

Oxfordshire County Council has restarted design work on the north west Bicester strategic link road, which would join the A4095 to Lords Lane through a railway underbridge built in 2021.

Work on the Bicester link road was paused in 2021, after a review of costs and the delivery of planned housing, so that more homes could be built and Section 106 developer funding secured.
With more houses now on site, the council has commissioned preliminary design, environmental and technical assessments, the planning application and preparation for detailed design.
In brief:
- Preliminary design should be finished in spring 2027, with the planning application submitted that spring and a decision expected in winter 2027.
- Around 6,000 homes and at least 3,500 jobs are planned in north west Bicester, plus a new secondary school the road would connect to.
- No construction start date has been confirmed.
What the north west Bicester link road would include
The route would run from the junction of the A4095, B4030 Middleton Stoney Road, Vendee Drive and Howes Lane to a new connection on Lords Lane. Previously known as the Howes Lane realignment and A4095 realignment scheme, it includes walking, wheeling and cycling facilities, bus infrastructure and highway improvements.
Planning permission for phase one was granted in 2019. That phase was completed in 2021 with the railway underbridge and a separate underpass for pedestrians, cyclists and horse riders. The council’s project page adds that developer Albion Land also completed a section of the road, and that the planning application will be considered by Cherwell District Council.
Funding has been secured for the design and planning work, the project page says. Construction still depends on future funding arrangements, although developer funding has already been secured from sites with planning permission. Building the full route also depends on planning approval, detailed design, land agreements and delivery arrangements with partners. A feasibility study is looking at future arrangements for part of the existing Howes Lane corridor, and no decisions have been made.
Councillor Liz Leffman, Oxfordshire County Council’s Cabinet Member for Highways Construction and Repair, said: “The strategic link road is an important investment in Bicester’s future. It will help support the sustainable growth of new houses, jobs and services by moving traffic away from existing homes, reducing queues and making it easier and safer for people to choose walking, wheeling, cycling and public transport for everyday journeys.”
She added: “Now that more houses have been built on site, we can move forward together with developers and other partners to develop proposals for the full route.”
Detailed design work is due to begin in spring 2027. The council says it will offer in-person and online chances to ask questions and give feedback alongside the planning application. In September we reported on a delay to an Oxfordshire relief road.
Source: Oxfordshire County Council, published 2 November 2026
In this story Oxfordshire County Council