Bury Interchange footbridge work starts in November, due early 2028

Work on a new Bury Interchange footbridge and tram platform upgrades starts later this month, ahead of a new bus and tram hub planned from 2028.

Image: Transport for Greater Manchester
A new 57-metre footbridge over the Metrolink tram lines is the first part of the Bury Interchange redevelopment, with work starting in mid-November 2026. Transport for Greater Manchester (TfGM) says phase one, which also upgrades the tram platforms, will finish in early 2028, and trams will keep running into Bury for most of the project.
In brief:
- The step-free Corten steel footbridge links Union Square to Pyramid Park, with a lift and stairs down to the Metrolink platforms
- Platforms will be resurfaced and get new canopies, ticketing, passenger information, driver facilities, lighting, signage and CCTV
- From mid-November part of the Metrolink car park becomes a site compound, with park and ride at Radcliffe and Whitefield as alternatives
Bury Interchange footbridge and the two-phase redevelopment
Planning permission for phase one was granted in July 2025, TfGM says. The footbridge has a 35-metre central span and two 11-metre approach spans, and it will stay in place when the interchange closes for its redevelopment, so passengers can still reach the tram platforms. Temporary stepped access at the north end of the eastern platform is due to open in late 2027 or early 2028, before the main interchange work begins. A June 2025 report to Bury’s Bee Network Forum described the bridge as a second, new access to the tram platforms.
Phase two, subject to approvals, would build a new enclosed interchange with an active travel hub and secure cycle parking, with construction expected to start in early 2028. TfGM is also exploring new rental apartments, which would need further consultation and planning approval, and wants Bury to become Greater Manchester’s first carbon-neutral transport hub. The public consultation is scheduled for winter 2026.
Phase one is funded through the government’s City Region Sustainable Transport Settlement, which awarded Greater Manchester £1.07bn, and Bury Interchange is a specified project within it. There will be times when trams can’t run into the interchange, with bus replacement services in those periods, and buses will keep running to and from the town centre throughout. Elsewhere in Bury, the council’s £12.9m highways investment programme went to its Cabinet on 14 October, as we reported.
Source: Bury Interchange project page, Transport for Greater Manchester