Cat and Fiddle road reopens three weeks early, 11-week closure to come

Derbyshire County Council has reopened the A54 Cat and Fiddle road almost three weeks early after phase one of a £3m repair programme. A second full closure follows in spring 2027.

The A54 Cat and Fiddle road reopened on Monday 12 October, having been closed to all traffic since 27 July.
It had been due to stay shut until 30 October. Derbyshire County Council says it will close again next spring for the second half of the job.
In brief:
- Phase one is complete of a £3m programme of repairs and safety improvements on the A54 between the A53 Leek Road junction and the A537 at the Derbyshire county boundary.
- The council says crews worked days and nights to finish almost three weeks ahead of schedule.
- Phase two is planned for spring 2027 and is expected to need another full closure of about 11 weeks. Dates haven’t been confirmed.
What the Cat and Fiddle road closure paid for
The A54 Macclesfield Main Road is the Derbyshire half of the Cat and Fiddle, the high moorland route that runs with the A537 between Buxton and Macclesfield. It’s exposed, wet and steep, and its earth banks have been falling onto the road. The council says that’s down to more extreme weather and inadequate drainage.
The summer closure allowed major excavations across the full width of the road. Phase one rebuilt sections of the road and laid new foundations, with measures to reduce surface water flooding, new road markings, reflective road studs, new kerbs and repaired signs. On a road like this, the foundations and drainage matter most. Water that can’t get away soaks into the layers beneath the surface and breaks the road up from below, and on an exposed moorland route that happens quickly.
Councillor Charlotte Hill, the council’s cabinet member for highways, said: “We know how important the Cat and Fiddle route is to residents, businesses and people travelling between Derbyshire, Cheshire and Staffordshire, so we are very pleased to be reopening it three weeks earlier than planned.” She added that completing the phase early was the result of careful planning and hard work, across days and nights throughout the programme.
Phase two deals with the hillside itself. It will involve reinforcing the earth banks to make them more stable, reducing the risk of soil and loose rock falling onto the road, and installing new safety barriers and bike guards as well as repairing existing ones. It will also replace drainage culverts under the road and complete the remaining resurfacing towards the A53 junction. The signed diversion will again use the A53, A523, A537 and A54. We reported in July on the £24m Derbyshire contract for the barrier you only notice after a crash.
The council hasn’t named the contractor or said how the £3m divides between the two phases. It says it will give clear information about dates and arrangements for the spring work as soon as they’re confirmed.
For drivers and the motorcyclists the route is famous with, the road is open for winter. Expect it to shut again once the weather turns in spring.
Source: Derbyshire County Council