Charterholme junction works in Lincoln must be done by 100th home

City of Lincoln Council has changed traffic management at the Charterholme junction works on Doddington Road after complaints about queues, adding manually controlled lights at Pershore Way at peak times.

A planning condition set the deadline, and the homes got there first.
The new signalised junction at Birchwood Avenue and Doddington Road in Lincoln has to be in place by the time the 100th home at Charterholme is occupied. With residents already moving in, the work couldn’t wait for the development’s spine road.
In brief:
- City of Lincoln Council and Lindum Group introduced traffic management changes at the junction from Friday 16 October.
- Temporary signals have been adjusted and manually controlled lights added at Pershore Way and Doddington Road during the morning and afternoon peaks.
- The junction improvement is expected to be complete in early spring 2027.
What is changing at the Charterholme junction works
The works began on 5 October. Since then, the council says, the project team has monitored traffic and, working with Lincolnshire County Council, main contractor PM Harris has agreed changes to reduce queues. The council says it and Lindum Group listened to concerns from residents, employees and visitors about congestion.
From 16 October, the temporary traffic signals have been adjusted to keep delays to a minimum. Additional temporary lights are being used at the junction of Pershore Way and Doddington Road during the morning and afternoon peaks, controlled manually to help traffic move along the diversion route. Where road closures are needed later, signed diversions will be put in place, with closure dates and diversion maps shared in advance through the Charterholme newsletter, website and social media.
The reason the works can’t be dropped lies in the planning consent. Lincolnshire County Council is the local highway authority. Its planning conditions require the junction improvement by the occupation of the 100th home, and the new spine road through the development by the 600th. The signalised junction is a requirement of the planning consent and, the city council says, will add capacity and safety benefits for all road users, including pedestrians and cyclists. The county council has approved the road closures and diversion routes.
Cllr Joshua Wells, Portfolio Holder for Inclusive Economic Growth at City of Lincoln Council, said: “Unfortunately, these works are unavoidable. We explored with the highways authority, Lincolnshire County Council, whether they could be modified or removed. However, they were quite clear that the works must proceed.”
He added: “We recognise the congestion and disruption residents and road users have experienced since these works began, and we have listened to the concerns raised.”
Conditions like these are common on large housing sites. They tie each piece of road infrastructure to a point in the build, so the network can cope as traffic grows. The council hasn’t given the cost of the junction or said when any closures will happen. Residents and businesses can contact the site team on 01535 331910. Our earlier report on a £1.9m highway improvement scheme in Lincoln covers another city junction programme.
Source: City of Lincoln Council