Cumberland permit scheme cuts time works occupy its roads by 28%

The Cumberland permit scheme has cut the average length of road and street works from 3.9 to 2.8 days, a council review finds, even though utility works ran higher than forecast.

Road and street works in Cumberland are finishing sooner, according to a review of the Cumberland permit scheme presented to the council’s Highways and Transport Strategic Board on Thursday 22 October.
The Cumberland Council Permit Scheme for Road and Street Activities Review 2023-26 found that the average duration of works fell from 3.9 days to 2.8 days.
In brief:
- The total time works occupied the highway network fell by 15,516 days, a reduction of 28%.
- Utility works stayed higher than originally forecast, averaging 12,391 works a year.
- The review found an increase in planned minor works and a reduction in urgent works.
What the Cumberland permit scheme review found
Permit schemes let councils manage when road and street works take place. Utility companies and other organisations carrying out works, known as promoters, must get a permit first. That gives the council more opportunity to co-ordinate activity, reduce the time roads are occupied and keep disruption down.
Cumberland Council became a unitary authority on 1 April 2023 and later approved its own permit scheme to replace the former Cumbria County Council scheme. The new scheme came into operation on 1 April 2025. The review covers the period from 2023 to 2026, so it spans both schemes. The council hasn’t said exactly which periods the before-and-after figures compare.
The council says that even with utility works running above the original forecast, the scheme has reduced the duration of works and improved co-ordination across the highway network. More planned minor works and fewer urgent works, it adds, give more opportunities for activities to be co-ordinated and managed.
Councillor Denise Rollo, Cumberland Council’s Executive Member for Sustainable, Resilient and Connected Places, said: “Road and street works are sometimes unavoidable, but it is important that they are planned and coordinated as effectively as possible to minimise disruption. These results show that our permit scheme is making a positive difference by reducing the time works occupy our roads and strengthening collaboration between the council, utility companies and other organisations.”
She added: “We will continue to monitor the scheme and work closely with those carrying out works across Cumberland to help keep people moving and limit disruption for residents, businesses and road users.”
The review concluded that the scheme continues to operate effectively. The council says it will keep monitoring permit applications, staffing requirements and permit fee income, so that the scheme remains effective, properly resourced and financially sustainable.
The council hasn’t given the number of permits issued, the fee income or a breakdown by promoter. Earlier this year, the council set out its £27.3m highways investment plan.
Source: Cumberland Council, published 23 October 2026