Final Dawsons Corner surfacing on £44m Leeds junction from 9 November

Dawsons Corner surfacing runs overnight from 9 to 29 November, with Leeds City Council closing lanes and roads in phases as the £44m junction scheme heads for completion in early 2027.

Final road surfacing on the Dawsons Corner and Stanningley Bypass improvement scheme in Leeds will run from Monday 9 November to Sunday 29 November.
Leeds City Council says a series of overnight lane and road closures will be needed across Dawsons Corner and surrounding routes, with roads and lanes reopening each morning.
In brief:
- Work will generally take place between 8pm and 5am, with contingency dates built in because surfacing can be affected by poor weather.
- Closures will affect different parts of Dawsons Corner, Bradford Road, Stanningley Bypass and Owlcotes Lane at different times, with signed diversions where required.
- The £44m scheme is due to be completed in early 2027.
How the Dawsons Corner surfacing will be phased
The council says the surfacing will be carried out in phases to help manage disruption. Access arrangements for New Pudsey Station will change during some phases, and temporary restrictions will be needed at the entrances to some residential streets. Residents and businesses directly affected will get separate information about access. Businesses including Owlcotes Shopping Centre will stay open as usual.
After the main surfacing programme, more overnight works are planned between 30 November and the end of December, with resident access maintained. The finishing stages also include final adjustments and tuning of the new traffic signals, landscaping and tree planting.
Around 57,000 vehicles and 1,200 pedestrians and cyclists use Dawsons Corner each day, the council says. Once complete, the scheme will provide improved walking and cycling connections, enhanced bus infrastructure, additional road capacity and new landscaping.
Councillor Tom Hinchcliffe, Leeds City Council’s executive member for transport and planning, said: “This scheme is a significant and complex undertaking. It’s running to time and budget, with many local residents set to benefit from the new road layout, Stanningley Bypass resurfacing and flood prevention.”
He said the scheme’s underground water attenuation tank “will prevent flooding and protect the new roads from damage, should we get heavy rain”. He added that the new Weaver Network bus stops are in place, ready to serve residents once buses are brought back into public control early next year, and that new crossings will support pedestrians and young people walking to nearby schools.
Our earlier report covered the contract award for the Dawsons Corner and Stanningley Bypass upgrade.
Source: Leeds City Council, published 23 October 2026