Galafoot Bridge works run to late January 2027 after deck found worse

BEAR Scotland now expects the A6091 crossing to stay open to westbound traffic only until late January 2027, after finding more than three times the concrete repairs it had planned for.

The Galafoot Bridge works will also shut the bridge in both directions from 19:30 to 06:00 on the nights of 2, 12–18 and 24 November.
Overnight closures that had been scheduled for 8, 9 and 29 November will no longer go ahead, BEAR Scotland said on 28 October.
In brief:
- Eastbound traffic has been diverted since 5 October via the A7 and the B6360, adding about 3.9 miles. Eastbound HGVs go via Selkirk, the A699 and the A68.
- BEAR Scotland is managing the project for Transport Scotland, with VolkerLaser resurfacing and re-waterproofing the deck and Geo-Structural working on the underside.
- When the programme was confirmed, the eastbound closure was expected to last six to 10 weeks.
Why the Galafoot Bridge works will take longer
Once the surfacing and waterproofing on the eastbound carriageway came off, the concrete deck slab underneath was found to be in much worse condition than estimated, said David Bishop, BEAR Scotland’s South East Bridges Manager. “There was always some uncertainty over what we would find once we removed the existing road surface, however there is more than three times as much concrete requiring repairs as originally anticipated,” he said.
He said the team had looked at bringing in extra resources to speed the job up, but the condition of the concrete under the westbound carriageway and the weather were still unknown. “Assuming the deck under the other half of the bridge is in similar condition, and we experience weather that would typically be expected during November and December, it is likely that works will need to continue until the end of January 2027.”
On the overnight closure nights, westbound traffic is diverted via the A6091 eastbound, the A68, the A699 and the A7 to Kingsknowe Roundabout. Access over the bridge for emergency services is maintained at all times.
BEAR Scotland flagged the risk at the outset. When it announced the refurbishment in July, it said the existing waterproofing under the surface course had failed, causing the road surface to break up prematurely, and that the overall duration would depend on the weather and the extent of the concrete repairs needed.
BEAR Scotland also carried out the recent Clackmannanshire Bridge closure on the A876 for drainage cleaning.
Source: BEAR Scotland via Traffic Scotland, published 28 October 2026
In this story Bear Scotland Ltd, Concrete Repairs Ltd, Transport Scotland