Kingswood roundabouts works in Hull to run until spring 2027

Hull City Council’s work to expand the Kingswood roundabouts at Wawne Road/Bude Road and Ennerdale, under way since March, is now due to continue until spring 2027 after utility diversion delays.

Every day, 32,361 vehicles pass through the Ennerdale roundabout and 30,814 through Wawne Road/Bude Road.
By 2040 the council predicts rises of nearly 10% at Ennerdale, to 35,393, and nearly 14% at Wawne Road/Bude Road, to 35,013. The investment followed the completion of several new housing developments in the area.
In brief:
- Working with local contractor CR Reynolds Ltd, the council has installed 1,036m of new drainage pipe, 40 new street lighting columns and attenuation tanks that can hold 326m³ of water.
- The schemes have laid 3,263m² of new carriageway and 3,419m² of new segregated footway, and removed 16,452 tonnes of soil and old road surfacing.
- Lane closures will be removed over Christmas and New Year wherever possible and where it is safe to do so.
What is left to do at the Kingswood roundabouts
At Wawne Road/Bude Road, new kerbing has been installed around the roundabout, Wawne Road widening has been completed apart from final surfacing, and new footways and cycle tracks are taking shape along Wawne Road towards Holwell Road. Next comes road widening along Holwell Road southbound, including a new splitter island, before switching to the northbound side shortly after.
At Ennerdale, Ennerdale Road is now open to all traffic after widening, and Thomas Clarkson Way widening is nearing completion. The remaining utility diversion works in the north verge must be finished before improvements can begin on the northern side of the roundabout.
The council confirmed the revised programme in September, citing delays to utility diversion works and additional utility requirements. Councillor Mark Ieronimo, cabinet portfolio holder for transport and infrastructure at Hull City Council, said: “Unfortunately, delays involving utility diversions have affected the construction programme, and we fully understand the frustration this has caused residents and motorists.”
When it appointed CR Reynolds in December 2025, the council said the schemes were funded through its capital programme and an allocation from the Ministry of Housing, Communities and Local Government, and that the main works would start in early March and be complete by the end of the year.
The schemes have provided work for 30 local staff and opportunities for five apprentices, the council says. CR Reynolds, based in Hessle, is also extending a footway within the campus of St Andrew’s School at the council’s direction. The release describes a multi-million-pound investment but doesn’t give a cost.
For more on the city’s roads, see our report on Hull’s highways investment programme.
Source: Hull City Council, published 26 October 2026