Limekiln Roundabout gets £400,000 drainage and resurfacing in Telford

Telford & Wrekin Council has invested £400,000 in a drainage and resurfacing scheme at Limekiln Roundabout. Here’s what the council says it has done, and how it fits its £91m highways programme.

Telford & Wrekin Council has invested £400,000 in a drainage and resurfacing scheme at Limekiln Roundabout, which it describes as one of the borough’s key routes. The council says the scheme was delivered in two phases and is designed to improve the condition of the carriageway, reduce future maintenance requirements and improve drainage at the busy junction.
In brief:
- Phase one covered drainage, with five new gullies and 60 metres of new carrier drain
- Phase two was the full resurfacing of the roundabout, covering approximately 9,400 square metres of carriageway
- The project also includes a further 600 square metres of repairs on nearby Telford Way, drainage cleansing and renewed road markings
What the Limekiln Roundabout resurfacing covers
The council says the first phase focused on drainage, with five new gullies and 60 metres of new carrier drain installed. The second phase saw the full resurfacing of the roundabout, approximately 9,400 square metres of carriageway. As part of the project, a further 600 square metres of repairs will be completed on nearby Telford Way, alongside drainage cleansing and the renewal of road markings.
The investment forms part of the council’s ongoing £91m programme of highway improvements across the borough over four years, which the council says helps maintain roads, footways, bridges, drainage systems, street lighting and other key assets. In May, the council launched a preventative road maintenance programme, as we reported.
Councillor Nathan England, the council’s Cabinet Member for Safer Streets and Better Housing, said Limekiln Roundabout is “a key route used by thousands of motorists every day”, so it is important to keep investing in maintaining and improving it. “This £400,000 scheme will not only provide a high-quality new road surface but will also improve drainage, helping to reduce future maintenance needs and improve resilience in wet weather,” he said. He added: “We appreciate that highway works can cause some temporary disruption, but these improvements deliver long-term benefits for road users and help keep people moving around the Borough.”
The council also says its long-term approach to investing in highways has helped it consistently achieve some of the highest resident satisfaction ratings for highways and transport services, both regionally and nationally.
Source: Telford & Wrekin Council, published 26 October 2026