Llanbedr relief road’s £40m cost exceeds North Wales’ £28m fund

A proposed £40m Llanbedr relief road in Gwynedd has no construction funding, and councillors fear it could swallow North Wales’ £28m Regional Transport Fund for 2026–27.

Members of the North Wales Corporate Joint Committee’s strategic transport sub-committee want the Welsh Government to explain how larger schemes could be funded without squeezing out other regional priorities. They discussed a Llanbedr position statement from Ambition North Wales on Monday 2 November.
In brief:
- A briefing note put phase one, the relief road, at £40m for 2026–30, with in-village traffic and environmental improvements adding £4m in 2030
- The Welsh Government has advised the region to assume a flat Regional Transport Fund budget for future years, with no inflation increase
- The Welsh Government has set up a group to look for a funding solution
Why the Llanbedr relief road is back on the table
Llanbedr, on the A496 between Barmouth and Harlech, has a narrow village road and a listed stone bridge over the Afon Artro. Traffic on Mochras Road towards Shell Island rises from around 150 vehicles a day in November to about 2,000 in August, according to 2006 figures cited in the Welsh Government’s 2021 review of an earlier scheme. That review panel’s report, published on 1 November 2021, described a 1.5km bypass west of the village with a 2018 cost estimate of £15m and a design speed of 100kph, and advised that it not be taken forward. A low-speed relief road is now proposed instead.
The committee report said: “The cost of the relief road alone is £40 million. The total RTF budget for North Wales for 2026/7 is c.£28m, we have been advised by Welsh Government to assume a flat budget (with no inflation related increase) for future years.” Development work has received Regional Transport Fund support in 2026–27.
Chair Cllr David A Bithell said: “I don’t think anyone disputes the fact it is needed,” but its funding needed clarifying, and proposed inviting the Welsh Government to the next meeting. Cllr Mike Priestley said: “We have such a small pot and we have so many projects across six north Wales authorities, such a large scheme could completely wipe out the budget.” The A55’s private operating contract for junctions 1 to 11 is due to end in 2028, as we reported.
Source: Fears £40m relief road scheme could jeopardise other transport projects, Nation.Cymru (Local Democracy Reporting Service), published 3 November 2026