M5 closure to clear 440 tonnes of concrete from Gloucester footbridges

The M5 closes both ways between junctions 11 and 12 near Gloucester from 11pm on Friday 16 October. Here’s the M5 closure Gloucester drivers need to plan for, the diversions, and what’s coming down.

For 64 years, two footbridges have carried pedestrians over the M5 near Gloucester. This weekend they come down. National Highways will close the motorway in both directions between junction 11 (Cheltenham) and junction 12 (Gloucester), including junction 11a, from 11pm on Friday 16 October until 6am on Monday 19 October, so contractors can demolish the Grove Court and Uphill Court bridges.
In brief:
- The M5 closes in both directions between junction 11 and junction 12, including junction 11a, from 11pm on Friday 16 October to 6am on Monday 19 October
- Both 69-metre footbridges have been closed since March after deteriorating beyond repair, and will be removed by high-reach excavators
- Replacement bridges are planned within the next five years, subject to funding and other network priorities
What the M5 closure at Gloucester involves
Each bridge is 69 metres long. High-reach excavators will dismantle them over the weekend, removing 440 tonnes of concrete and 14 tonnes of steel tendons from the carriageway before the road reopens. Tendons are the high-strength steel strands used to hold a prestressed concrete structure in compression.
The bridges have been shut since March because they have deteriorated beyond repair. We first reported the problem in September, when National Highways said edge beams were crumbling onto the carriageway below: two bridges, one motorway closure, and the falling concrete behind the Gloucester M5 job.
Terry Robinson, South West Engineering Lead for National Highways, said:
“Like many of our motorways and structures, the bridges have exceeded their structural lifespan, and replacing them will ensure the safety of road users and keep people and goods moving safely.” He added: “We’ve communicated the closure to local communities and businesses, but we appreciate the weekend closure will still have impacts for the travelling public.”
The weekend M5 closure follows an earlier restriction. The M5 northbound junction 11a exit slip road has been closed 24 hours a day since 8pm on 11 October for about two weeks, and drivers can still leave the motorway at junction 11.
During the M5 closure, traffic will be diverted in both directions via the A38 through Gloucester, the A40 between Cheltenham and Gloucester, and the A417. National Highways says the routes have been planned to lessen conflict with the bridge works on the A40 at Over, and that the 11pm Friday start allows people to attend Gloucester Rugby’s European Champions Cup match against Union Bordeaux-Bègles. Gloucestershire County Council says the works are expected to have a significant impact on traffic in and around Gloucester, and that it is working closely with National Highways.
The motorway is expected to reopen in time for Monday morning commuter traffic. National Highways advises drivers to plan ahead, consider alternative routes, and allow extra time, with diversion maps on its website and live updates on its travel alerts page.
The new bridges will be built to modern standards, with safe access for pedestrians, cyclists and wheelchair users. National Highways hasn’t given a cost or named the contractor.
In this story National Highways, Gloucestershire County Council