M5 footbridge demolition at junctions 11 and 12 finishes early

The M5 between junctions 11 and 12 near Gloucester reopened on Sunday evening, ahead of its planned 6am Monday finish, after National Highways demolished the Grove Court and Uphill Court footbridges.

The weekend closure for the M5 footbridge demolition near Gloucester finished early.
National Highways closed the motorway in both directions between junctions 11 (Cheltenham) and 12 (Gloucester) from 11pm on Friday 16 October to demolish two 64-year-old footbridges. Both were down and cleared in time for the road to reopen on Sunday evening, hours before the planned 6am Monday reopening.
In brief:
- The M5 between junctions 11 and 12 reopened on Sunday 18 October, ahead of schedule, after the Grove Court and Uphill Court footbridges were demolished.
- Around 440 tonnes of concrete and 14 tonnes of steel tendons were removed from the carriageway.
- The concrete and other material from the bridges is being processed at the site compound for recycling.
How the M5 footbridge demolition at junctions 11 and 12 finished early
The two bridges, each about 69 metres long, carried public footpaths over the motorway. They had been closed to pedestrians since March, after their concrete edge beams deteriorated badly. National Highways said they had to come down before they became a hazard to traffic below.
Demolishing a bridge over a live motorway is a race against the clock. Once the structure is brought down, the debris has to be broken up and cleared from the carriageway before the road can reopen. Here, that meant clearing around 440 tonnes of concrete and 14 tonnes of steel tendons, the high-strength cables that held the prestressed concrete beams in compression.
Preparation helped. The northbound exit slip road at junction 11a had been closed since 11 October and used as a works compound, so the plant and equipment were already on site when the motorway closed. National Highways had said storing them anywhere else would have meant a longer closure. The compound is now being used to process the demolished material for recycling. National Highways says drivers can join the M5 northbound and southbound at junction 11a as normal. The northbound exit slip was expected to stay closed for around two weeks from 11 October while the compound is cleared.
New Grove Court and Uphill Court bridges are planned, with safe access for pedestrians, cyclists and wheelchair users, subject to funding and other network priorities. National Highways hasn’t given a date. We covered the closure and the reasons for the demolition on Friday: M5 closed near Gloucester between junctions 11 and 12 for footbridge demolition.
For drivers between Cheltenham and Gloucester, the motorway is open again. For walkers who used the two footpaths, the wait for replacement bridges begins.