M5 junction 10 slip roads to close for around two years from 2027

The M5 junction 10 northbound entry and southbound exit slip roads are expected to close for around two years from early 2027. Gloucestershire County Council is holding five public information events first.

Drivers won’t be able to join the M5 northbound or leave it southbound at junction 10 for around two years.
Gloucestershire County Council says the closures of the existing northbound entry and southbound exit slip roads are expected from early 2027, as its M5 Junction 10 Improvements Scheme reaches its next major stage. The motorway itself stays open.
In brief:
- The northbound entry and southbound exit slip roads at junction 10 are expected to close for around two years from early 2027.
- Withybridge Lane will also be closed. The A4019 stays open, with temporary traffic management at times.
- Five public information events run between 4 and 26 November.
Why the M5 junction 10 slip roads must close
The council says the slip roads need to close so the most complex parts of the work can be carried out as safely and efficiently as reasonably possible. It considered other ways of doing the work and managing traffic, and believes a single closure is the best option, instead of opening and closing the slip roads at different stages or repeatedly changing access. The exact duration is still being reviewed.
Cllr Julian Tooke, Cabinet Member for Business, Economic Development, Planning and Infrastructure, said: “We know this will be difficult for people who use junction 10 and nearby roads, including Withybridge Lane which will also be closed. Different construction and traffic management approaches have been considered, but some options do increase safety risks, cost more, create more changes for drivers or extend motorway traffic management.”
The council and its partners, including National Highways, are still reviewing the approach. Andrew Jackson, Programme Leader at National Highways, said: “One of our priorities is to minimise disruption for people using our roads during any works, which is why we are working closely with Gloucestershire County Council during planning and while this important junction is upgraded.”
Diversion routes haven’t been published. The project team is looking at how the closures could affect nearby roads and communities, including whether drivers may use unsuitable local roads to avoid the diversions, and says more will be shared as plans are finalised.
The £372m scheme will make junction 10 an all-movements junction, so drivers can join and leave the M5 in all directions for the first time. It also includes a new link road from the A4019 to the B4634 in west Cheltenham, widening of the A4019 Tewkesbury Road, new active travel facilities and flood mitigation. The council says the junction will enable more than 20,000 new homes, including over 7,000 affordable homes, and support the Golden Valley development and National Cyber Innovation Centre in creating around 12,000 skilled jobs.
Funding so far includes the UK Government’s Housing Infrastructure Fund, administered by Homes England, district council Community Infrastructure Levy, the county council and section 106 contributions from developers. Our earlier report covered how the £372m M5 improvement scheme was set to progress despite rising costs.
The public information events, where people can see plans and visualisations and ask about the construction programme, diversion routes and traffic arrangements, are:
- Wednesday 4 November, 10am–3pm: West Cheltenham Community Fire Station
- Thursday 5 November, 3pm–8pm: West Cheltenham Community Fire Station
- Tuesday 17 November, 10am–2pm: Hesters Way Community Resource Centre
- Wednesday 18 November, 3pm–7pm: The Watson Hall, Tewkesbury
- Thursday 26 November, 2pm–7pm: Stoke Orchard Community Centre
Source: Gloucestershire County Council, published 21 October 2026