National Highways contractors for 11 areas and the £8bn retender

Our guide to National Highways contractors: who maintains each area of England’s motorways and major A roads, the frameworks that buy renewals and big schemes, and the contracts being retendered now.

National Highways owns England’s motorways and major A roads, but it buys the work on them from contractors. Five firms hold the area maintenance contracts that keep the network running day and night. Dozens more sit on frameworks for resurfacing, barriers, markings, technology and major schemes. Many of those deals end between 2026 and 2029, so most of the work is being retendered.
In brief:
- Ringway, Kier, Amey, Colas and a CH2M Hill and Costain team hold the area maintenance contracts, and Connect Plus runs the M25.
- All the maintenance contracts now end between June 2028 and July 2029, when an estimated £7.96bn replacement takes over.
- The renewals framework is being replaced by an estimated £14.5bn successor, with 64 lots, due to start in September 2027.
Last updated: 28 October 2026
How do National Highways contractors win the work?
National Highways (formerly Highways England, renamed in August 2021) runs the strategic road network in England. It buys work through three main routes:
- Area maintenance contracts for everyday upkeep and incident response
- Frameworks for renewals such as resurfacing, barriers and drainage
- Delivery partnerships for big improvement schemes
Specialist frameworks cover technology, consultancy and concrete roads.
The money is set by the government in five-year road investment strategies. The second, RIS2, gave £27.4bn for 2020 to 2025. After a one-year interim settlement of £4.84bn for 2025-26, RIS3 runs from April 2026 to March 2031. It provides more than £27bn in all, including £24.99bn to operate, maintain, renew and enhance the network, with £8.44bn of that for renewals and £3.85bn for enhancements. In 2025-26 National Highways spent £1.51bn on enhancement schemes and £1.26bn on renewals, according to the Department for Transport’s performance report. Our projects coverage follows the schemes.
Which National Highways contractors maintain each area?
England’s network is divided into areas. In each area a maintenance and response (M&R) contractor handles routine and cyclical maintenance, defect repairs, incident response and severe weather, including winter gritting. In August 2025 National Highways changed every contract so they end between June 2028 and July 2029, ready for a single retender.
| Area | Contractor | Value | Ends |
|---|---|---|---|
| South West (1 and 2) | Ringway | £405.5m | Jun 2028 |
| Area 3 | Kier | £288.7m | Jun 2028 |
| Area 4 | Kier | £238.5m | Jun 2028 |
| Area 5 (M25) | Connect Plus | DBFO | 2039 |
| East (6 and 8) | Ringway | £607.7m | Jul 2029 |
| Area 7 | Amey | £557.4m | Jul 2029 |
| Area 9 | Colas | £407.6m | Jul 2029 |
| Area 10 | Amey | £468.3m | Jun 2029 |
| Area 12 | Amey | £257.3m | Aug 2028 |
| Area 13 | Kier | £242.6m | Jun 2029 |
| Area 14 | CH2M Hill and Costain | £165.6m | Jun 2028 |
Values are the estimated contract values in National Highways’ change notices of 12 August 2025. £ figures in this table are rounded. Area 3 covers Hampshire, Surrey, Berkshire, Oxfordshire and parts of Dorset and Buckinghamshire. Area 4 is Kent, Surrey and Sussex. Area 7 is the East Midlands, Area 9 the West Midlands, and Area 10 Cheshire, Greater Manchester, Merseyside and Lancashire. Area 12 is Yorkshire and the Humber, Area 13 Cumbria and Lancashire, and Area 14 Northumberland, Tyne and Wear, County Durham and North Yorkshire. Area 5 is run by Connect Plus under a 30-year design, build, finance and operate (DBFO) contract signed in May 2009. Connect Plus is a consortium that includes Edge Orbital Holdings, Balfour Beatty and Egis.
Several of these firms are our partners. Amey lists its Area 7 and Area 10 maintenance contracts in its November 2025 carbon reduction plan. Ringway’s East team, which runs the old Areas 6 and 8, was named a finalist at the National Highways Industry Awards in March 2024. In 2023 Kier marked 20 years of Area 13, having been its principal contractor for 13 of them. The August 2025 change cut that contract’s end date from 2032 to June 2029.
What replaces the maintenance contracts?
Maintenance and Response 2. National Highways estimates it at £7.96bn over seven regional lots: South West, South East, East, West Midlands, East Midlands, North West, and Yorkshire and North East. The largest lot, the South East, is worth about £1.09bn. According to the tender notice, contracts are expected to run for about eight and a half years from 2028, with start dates staggered over about 12 months, and a single supplier will be appointed for each region. Requests to take part closed on 26 October 2026, and the award decision is expected in November 2027. We covered the launch in our report on the £8bn M&R2 deal.
That means the area map will change. There will be seven regions instead of the current 11 contracts.
Which National Highways contractors do the renewals work?
Most renewals go through the Scheme Delivery Framework, announced in September 2021. Its 50 suppliers share up to £3.6bn of work in four bands: civils and drainage, traffic management and road restraint, specialist works, and design. Surfacing has its own £1.3bn Pavement Delivery Framework, which runs to December 2027 and uses 12 firms including Tarmac, Aggregate Industries, Hanson, FM Conway, Eurovia and Galliford Try.
Our partners hold places across both frameworks:
- Tarmac won a Pavement Delivery Framework place in December 2022
- Chevron TM holds the Central temporary traffic management lot on the Scheme Delivery Framework
- WJ holds road markings lots for the North West and the Midlands
- Crown Highways won road lighting and electrical, and technology lots in December 2021
- Eurovia holds the largest single award, £144.5m in the South general civils lot
For more on the firms behind the cones, see our guide to UK traffic management.
Both are due to be replaced by Scheme Delivery Framework 2, which is being procured now. It is estimated at £14.5bn over eight years from September 2027, split into 64 lots: a national main contractor lot and a national tunnels lot, then regional lots for general civils, drainage and concrete, pavements, structures, traffic management, vehicle restraint, road markings, signs and lighting, joints and waterproofing, landscaping, technology design and design.
Concrete roads have their own framework. In February 2026 Kier, John Graham and John Sisk won places on the £968m Legacy Concrete Roads Reconstruction framework, which runs for six years, covering RIS3 and the start of RIS4.
Who builds National Highways’ big road schemes?
Major schemes have mostly gone through the Regional Delivery Partnerships. Highways England awarded them in November 2018: up to £8.7bn of work, 13 delivery partners and eight regional lots. Partners included Balfour Beatty, BAM Nuttall, Costain, Galliford Try, Kier, Skanska and VolkerFitzpatrick, each designing and building schemes. The framework was extended to 28 February 2026. National Highways published early plans in 2023 for a successor, the Integrated Delivery Framework, worth £20bn to £30bn, but we have not found a tender notice for it.
The biggest live contracts:
- Lower Thames Crossing. Bouygues Travaux Publics and Murphy hold the tunnels contract (£1.34bn), Balfour Beatty the roads north of the Thames (£1.14bn) and Skanska the Kent roads (£435m). The scheme won development consent in March 2025. RIS3 provides £1.65bn for its publicly funded works, and early works have started.
- A428 Black Cat to Caxton Gibbet. Skanska is building it. National Highways calls the £1bn scheme its largest in construction, with most of it opening in spring 2027 and the rest in mid-summer 2027.
- A66 Northern Trans-Pennine. National Highways named Balfour Beatty, Costain, Keltbray and Kier as delivery partners in 2022. RIS3 has work beginning early in the road period.
- M25 junction 10, Wisley. Balfour Beatty’s £317m scheme was due to finish in spring 2026.
Some schemes have gone. The A303 Stonehenge tunnel was cancelled in July 2024. The A12 Chelmsford to A120 widening and the A47 Wansford to Sutton dualling followed in summer 2025. The government has also said it will build no new smart motorways, which affects the £4.5bn Smart Motorways Alliance set up in 2020. Read our report on new smart motorways being scrapped.
Which specialist frameworks do National Highways contractors use?
- Technical consultancy. The £495m Specialist Professional and Technical Services 3 framework runs for six years from June 2025. Its six suppliers are Jacobs and AtkinsRéalis jointly, Costain, WSP, Arcadis, Arup and Amey.
- Roadside technology. The Operational Technology Commercial Framework covers detector, informing, passive and operational systems, plus consultancy support. It has been extended to January 2028 at £600m across 62 suppliers.
- Signs and signals. In December 2025 RIS3 contracts went to SWARCO, Colas and P. Ducker Systems.
For the council side of the market, as opposed to National Highways contractors, see our list of council highways contractors.
Source: National Highways, Maintenance and Response 2 tender notice, published 24 August 2026, and the primary sources linked in each section, checked on 28 October 2026.