Nether Bridge in Kendal gets 10m parapet rebuilt with original stones

Nether Bridge in Kendal is closed to vehicles for up to five days from 12 October while Westmorland and Furness Council rebuilds a parapet damaged in June, reusing original stone where possible.

A 10-metre section of the southern parapet on Kendal’s Nether Bridge was demolished in a traffic incident in June.
This week, it’s being rebuilt with as much of its original stone as can be saved, with the bridge closed to all vehicles from Monday 12 October for a maximum of five days.
In brief:
- Westmorland and Furness Council is rebuilding the damaged section of the bridge’s southern parapet under a 24-hour closure lasting up to five days.
- Original heritage stonework recovered from the site will be reused where possible, supplemented by locally sourced stone, and laid in traditional lime mortar.
- Pedestrians and cyclists can still cross throughout the works, using the northern footway.
What the closure of Nether Bridge in Kendal involves
The work is on the parapet, the low wall along the edge of the bridge deck. It isn’t an ordinary masonry job. Nether Bridge is a Scheduled Ancient Monument, and the River Kent it spans is both a Site of Special Scientific Interest and a Special Area of Conservation.
That designation shaped the whole method. Rebuilding a parapet is often done from scaffolding in the river below, but that would have needed environmental permits and could only happen in the next permitted river working window, in summer 2027. Instead, the council is doing the entire repair from the bridge deck. That’s why the bridge has to close: the site vehicles, access equipment, masonry and mixing equipment take up most of the carriageway, leaving no safe lane for traffic.
The material matters too. The repairs use traditional lime mortar to preserve the bridge’s historic character. Lime mortar is softer and more porous than modern cement mortar, which lets old stonework flex and breathe instead of cracking around a stiffer joint. But it sets slowly and needs time to cure before frosts arrive. The council says the October timing gives it that time before the colder winter weather sets in.
For drivers, a signed diversion is in place via Romney Bridge and Milnthorpe Road. Extra signs will stop HGVs using Parkside Road, because of the height restriction at the railway bridge there.
The council hasn’t said what the repair costs or who is carrying it out. Structures are one part of its highways workload. In June it set out a £3.4m surface dressing programme across Westmorland and Furness.
If the work runs to plan, vehicles will be back on Nether Bridge by the end of the week, crossing beside a parapet rebuilt, as far as possible, from its original stones.
Source: Westmorland and Furness Council