Newark Road closure of up to 7 weeks for North Hykeham Relief Road

Lincolnshire County Council is diverting utilities so the new five-mile North Hykeham Relief Road can join the existing network, bringing 24/7 lights on the A607 and an inbound Newark Road closure.

The Newark Road restriction starts on Monday 4 January 2027 and covers inbound traffic only, towards Lincoln, near the A46/A1434 junction at Pennells Roundabout, for up to seven weeks.
Outbound traffic leaving Lincoln stays open. Inbound traffic is diverted via the A46 northbound and the A57/Saxilby Road, with local signs for North Hykeham and south Lincoln.
In brief:
- The A607 lights start on Monday 16 November and run for up to one month, for Anglian Water utility diversion works ahead of a new roundabout.
- The council aims to have the Grantham Road signals off by mid-December and inbound traffic back on Newark Road by late February 2027, subject to weather.
- Balfour Beatty is building the road, with £110 million from the Department for Transport’s Large Local Majors programme.
Why the North Hykeham Relief Road needs a Newark Road closure
Both sets of restrictions are for utility diversions needed before new roundabouts can be built. “Once the new five-mile relief road is open, changes to the existing network will help encourage more traffic, including HGVs and commercial vehicles, to use the relief road rather than routes through the urban area,” said Cllr David East, executive member for highways at Lincolnshire County Council. “Achieving this will involve preparing junctions, coordinating utility infrastructure and making the connections needed to integrate the new road with the existing network.”
Construction began in March 2026, and the council’s project page lists new roundabouts at South Hykeham Road, Brant Road and Grantham Road, with completion projected for summer 2029. The rest of the funding comes from the county council and developer contributions.
Anglian Water also worked on the scheme’s drainage and utility systems, the council said earlier this month, as we reported on the relief road’s drainage, which will handle roughly 600 million litres of rainwater a year.
Source: Lincolnshire County Council, published 28 October 2026