Resin, steel mesh and incinerator ash: the seven methods in Cambridgeshire’s peat road repair trial

Seven repair methods are being tested side by side on the B1099 Upwell Road in March, Cambridgeshire, in a £1.5m trial to find which holds up best on roads built on peat.

Seven 150-metre sections of the B1099 Upwell Road in March have been dug up, and each one is being rebuilt a different way.
The peat road repair trial is Cambridgeshire County Council’s attempt to answer a question that costs it millions every year: what kind of repair actually lasts on a road built over peat?
In brief:
- Seven repair techniques are being tested on seven 150-metre sections of the B1099 Upwell Road in March, near its junction with the B1098 Sixteen Foot Bank.
- The trial is funded by a £1.5m grant from the Cambridgeshire and Peterborough Combined Authority, and Winvic Construction Ltd is the contractor.
- Each section will be monitored for at least 12 months to build evidence for future highways investment.
What the peat road repair trial is testing
Peat is a difficult material to build a road on. It moves and settles, so roads built over it crack, sink and break up faster than roads on firmer ground. The council says repairing them often means deeper reconstruction and costs four to five times as much as standard maintenance. Cllr Alex Beckett, who chairs its highways and transport committee, has said peat-affected roads last less than half as long as others.
That’s a large problem in Cambridgeshire. Around 40% of the county is underlain by peat, including 97% of Fenland and large parts of East Cambridgeshire and Huntingdonshire, and more than 1,800km of its roads are built on challenging ground. Cllr Beckett has linked the problem to the council’s £800m maintenance backlog.
The council’s chosen techniques include deep soil mixing, chemical stabilisation and alternative lightweight materials to strengthen the road foundation. Deep soil mixing blends binding agents straight into the peat beneath the road to stiffen it. Lightweight materials take a different approach: they reduce the load pressing down on the peat instead of trying to strengthen it. The council and Winvic set out the full range of sections to reporters on site on Thursday 8 October. They include a control section built with the current repair method, steel mesh reinforcement within the road structure, a cellular confinement system to spread traffic loads, and resin injection drilled into the carriageway in a grid.
Building them side by side is what makes the trial useful. Every section carries the same traffic, sits on the same ground and faces the same weather, so differences in performance come down to the method. The council chose Upwell Road because it is built over peat, carries heavy and agricultural traffic like many similar rural routes, and was due for renewal anyway.
Cllr Beckett and Paul Bristow, Mayor of Cambridgeshire and Peterborough, visited the site with the council’s project team and Andy Harmon, framework manager for Winvic. Alongside the trial, the council has resurfaced Upwell Road from the roundabout with Cavalry Drive to Binimoor Road. We covered the council’s wider repair plans in July, in our piece on its bid to patch roads before winter.
The council receives no extra funding for the higher cost of maintaining roads on peat. If one of these seven methods proves itself, the bigger question will be how to pay for it across 1,800km of road. For other highway authorities with roads on peat, including neighbouring Norfolk and Lincolnshire, the results will be worth watching.
In this story Winvic Construction Ltd, Cambridgeshire County Council