Private road repairs fall to owners, not councils, under 1980 Act

On a private road, the potholes belong to the people who live there. Here’s how private road adoption works in England, why it’s slow and expensive, and what home buyers should check first.

On a private road, the potholes belong to the people who live there. A private street, often called an unadopted road, isn’t maintained at public expense, and getting it adopted is slow and expensive.
In brief:
- Private roads are maintained by their owners, not the council, though a council may fence off a dangerous defect
- Most new estate roads become public through a Section 38 agreement with the developer
- Existing private streets can be adopted, but owners usually have to pay to bring them up to standard first
Private road adoption: who is responsible, and how it works
The law described here is the Highways Act 1980, which applies in England and Wales, and the Department for Transport’s guidance covers England. Scotland and Northern Ireland have their own systems.
The cost of a private road falls on whoever owns it. That is usually the residents whose homes front onto the road, sometimes a developer or management company, and on some older streets the owner can’t be traced. Hackney Council’s guidance on private streets says that, as highway authority, it is “under no obligation to carry out repairs or cleansing to the street.” Where a defect is dangerous, it says, the council may make it safe with barriers or closures, but permanent repairs are still down to the owners.
The DfT adds that until a new road is adopted, the developer or management company stays responsible for it, including for slips, trips and spills, and buyers may be liable for the access way outside their property.
Private doesn’t always mean closed to the public. A private street can still carry a public right of way, and highway and traffic law can still apply to it.
For new estates, the usual route is a section 38 agreement under the Highways Act 1980. The developer builds the road to the council’s standard, pays fees, and puts up a bond; maintains it for a maintenance period, usually 12 months; and then the council issues a certificate to adopt it. The DfT’s advice note on highways adoption calls this “the most common method of achieving road adoption”, and suggests buyers ask their solicitor whether an agreement is in place before they buy. It adds that buyers shouldn’t assume a road will be adopted.
Where there is no agreement, the options are harder. An owner can offer the road under section 37 with at least three months’ notice, but the council can refuse if it judges the road lacks sufficient wider public benefit, and the DfT notes that residential cul-de-sacs may have limited, if any. A council can adopt a finished street by notice under section 228, but the DfT says the owner “has an effective veto” in some cases, though the council can apply to the Magistrates Court to overrule an objection. Under the Private Street Works Code, a council can do the work itself, recover the cost from the frontagers, and then adopt the road.
That last route is rare. The DfT says it is “used in rare circumstances predominantly due to the costs and time incurred,” and councils generally want 80 to 100% of frontagers on board and committed to paying. Owners can challenge how the bill is split, and can object if the final cost runs more than 15% over the estimate without good reason.
For councils, every adopted road is an ongoing cost, and Hackney says it generally has no budget to help. That’s why most will only take on streets built to current standards. It’s a problem we’ve covered for years, from residents paying to fix their own streets to a council that cleared more than 100 tonnes of fly-tipped waste from unadopted roads.