What it takes to lift a Shrewsbury street by 100mm

Kier will raise part of Shrewsbury’s Raven Meadows by up to 100mm for a new crossing point, with a Raven Meadows road closure overnight on weeknights from 21 October to 4 November.

Raven Meadows in Shrewsbury is about to get up to 100mm taller, and it will take two weeks of nights to do it.
Shropshire Council has confirmed that Kier Infrastructure will build a raised table pedestrian crossing point on the town-centre street. The road will close fully from 8pm to 6am on weeknights between Wednesday 21 October and Wednesday 4 November 2026.
In brief:
- Raven Meadows, Shrewsbury, closes fully 8pm–6am on weeknights from 21 October to 4 November 2026.
- Kier Infrastructure is building a raised table crossing point for Shropshire Council.
- The table will be 65–100mm high, about 9m long including ramps, and run the full width of the carriageway.
- Access is kept for the hotel, multi-storey car park and businesses. Other traffic follows a signed diversion.
What the Raven Meadows road closure means after dark
Raven Meadows normally runs as part of a one-way system. While the works are on, that system will be rescinded, which is the formal term for switching it off. Vehicles can then reach the hotel, the multi-storey car park and the businesses along the street from the open end.
Pedestrians, dismounted cyclists and horse riders keep their access, as do emergency vehicles on blue lights. Deliveries to The Darwin shopping centre will go through the bus station. Everyone else follows a signed diversion, and the council says some drivers may have a choice of route depending on their vehicle type. It is also asking people not to leave vehicles parked on the road during working hours, because an obstructed site means a slower job.
The council hasn’t said why it chose night working, but the reason isn’t hard to work out. Raven Meadows serves a bus station, a multi-storey car park and a shopping centre. Shutting it at 10am on a Tuesday would hurt far more than shutting it at 10pm.
The feature itself is modest. According to the council’s public notice from June, the table will usually stand between 65mm and 100mm high. It will be about 9m long including the ramps, and it will cover the full width of the carriageway. It sits about 44 metres northeast of the junction with the road behind the multi-storey car park.
A raised table is a flat-topped hump. Drivers ride up a short ramp, cross a level plateau and come back down. The change in vertical alignment does the speed management, so no signals or police enforcement are needed. Because the table runs from kerb to kerb, a driver can’t straddle it the way they can with a speed cushion.
The council hasn’t published its construction method. On schemes like this, though, the hard part usually isn’t the hump. It’s the water. Raising the full width of a road changes how surface water runs off, so the table, the ramps and the existing gullies all have to be designed to work together. If they aren’t, the crossing point turns into a puddle.
One point worth being clear on: this is a crossing point, not a zebra. Drivers have no legal duty to stop for someone waiting on a raised table in the middle of a street. What the table does instead is slow vehicles down and lift the carriageway much closer to kerb height. That makes crossing easier for anyone pushing a buggy or using a wheelchair, and it makes the crossing place obvious to drivers. It works through physical design and doesn’t rely on legal priority.
The street has already changed a lot in recent years. In September 2024, two footbridges over Raven Meadows were removed during demolition work for the Smithfield Riverside regeneration. One linked the former Riverside Shopping Centre to the multi-storey car park, and the other led to the former Pride Hill Shopping Centre. The council hasn’t connected the new crossing to that project. Even so, a street that used to carry people overhead now needs to cater for them at ground level.
The legal groundwork was laid in the summer. The council published its notice proposing the traffic-calming measure in June, and the deadline for representations was 3 July 2026. Its latest announcement doesn’t say whether any objections came in.
For drivers who use Raven Meadows regularly, the change after 4 November will be small: a new hump and a reason to arrive more slowly. For anyone heading to the car park or hotel in the evening during the works, the useful details are the diversion signs and the temporarily two-way access. For the sector, it’s a neat example of how much planning goes into a 9m piece of road.