Sidewinder® | 250% improvement using Sidewinder® Offset Paver


Swale Construction Improved 250% using Sidewinder® Offset Paver.
Trials conducted during the construction of the North Norwich Distributor Road showed an increase in efficiency of 250% by using SidewinderUK® plant, as against conventional methods.
Sidewinder® offset paver is a unique plant able to lay any granular material to either side of an existing carriageway. Baseline measures conducted on the Balfour Beatty Norfolk project showed that 100 linear metres of swale could be completed in a day using conventional methods. Working with Sidewinder® plant, it was possible to lay 350 linear metres in a day – an impressive increase of 250%.
Richard Haley, Technical Manager at SidewinderUK®, said “We are always happy to go the extra mile and in this case we had to make alterations to our equipment in order to meet the high expectations of the Balfour Beatty team. Because we’re a small team, we were able to take decisions and act quickly to meet tight deadlines”.
“During this project”, Richard continued, “we offered unique solutions which involved manufacturing a completely new screed, the manufacture and trial of an extended auger, manufacture of an extension conveyor as well as creating a bespoke trapezoidal roller for the project”.
The research was carried out by section engineer Alexandros Charalampakis, who was managing the project for Balfour Beatty. For more information on SidewinderUK’s® solutions, contact Rhoda Shelton on 07766 178747 or email her on rhodasocialeready@gmail.com
To read the full report go here: https://www.sidewinderuk.com/sidewinder-improved-efficiency-swale-construction/
Stay sharp
Never miss a story
The daily highways digest, straight to your mailbox.
You will get a confirmation email. Unsubscribe anytime. About The Highways Industry Newsletter →