Five overnight closures to go: the Stafford Gate roadworks beside M6 junction 14

Overnight closures for surfacing start on 19 October as the Stafford Gate roadworks beside M6 junction 14 enter their final phase. Here’s the timetable, the closures and who is paying.

The cones beside junction 14 of the M6 in Stafford now have a finish date. Staffordshire County Council says the Stafford Gate roadworks on the A5013 Creswell Grove have reached their final phase, with overnight surfacing from Monday 19 to Friday 23 October and traffic management on that section due off by the weekend of 31 October.
In brief:
- Junction and road widening on the A5013 Creswell Grove at Creswell, next to M6 junction 14, is entering its final phase
- Full overnight closures from 10pm to 6am are planned from 19 to 23 October for surfacing, with a signed diversion, and traffic management on this section is due off by the weekend of 31 October
- The scheme serves a commercial development by Strawsons Property, which is fully funding the works
Who is paying for the Stafford Gate roadworks, and what’s left?
This isn’t a council-funded improvement. The road scheme is for a commercial development by Strawsons Property, which is paying for all of it. The council’s scheme page lists the works as a Section 278 scheme, the usual route for developer-funded changes to the public highway, with the highway authority setting standards and approving the design.
Work began in May, with a one-way order in place towards Stafford so that the work could be carried out safely. The council’s scheme page says the order will be removed after the works. The surfacing nights are the last big piece. Full closures of this section run from 10pm to 6am on 19 to 23 October, with a signed diversion in place. Full closures generally let a crew lay a new surface without live traffic alongside. The release doesn’t give the diversion route, so check the council’s scheme page.
Even after that, there’s one more stage. The last part of the scheme is east of junction 14, where a new pedestrian refuge will be installed and the roundabout will get some resurfacing, under temporary traffic signals. A pedestrian refuge is an island in the middle of the carriageway that lets people cross one direction of traffic at a time.
Patrick Allen, Cabinet Support Member for Highways at Staffordshire County Council, acknowledged the disruption. “It is close to a major junction and we understand the traffic management has caused disruption, but we’ve worked with the developer to ensure it has been carried out as quickly as possible,” he said. He added that the scheme “supports a significant development which will create jobs in the local area and provide a range of leisure facilities”, and thanked residents and the travelling public for their patience.
Elsewhere in the county, Staffordshire is delivering a £15m, two-year programme of road repairs.
In this story Staffordshire County Council