180,000 vehicles a day cross these joints. Thelwall Viaduct is getting new ones

A 24/7 contraflow starts on the M6 on 12 October as Thelwall Viaduct works step up, with National Highways replacing worn-out bridge joints in a £27m scheme running until winter 2027/28.

In 2014, the Highways Agency replaced six expansion joints on Thelwall Viaduct in nine weeks, for £2.5m.
This time, National Highways is spending £27m, and the job will run until winter 2027/28. The scope isn’t directly comparable, because this scheme covers the joints on both of the viaduct’s structures. Still, the Thelwall Viaduct works are on a different scale, and from Monday 12 October drivers will feel it around the clock.
In brief:
- National Highways is replacing the bridge joints on both the northbound and southbound Thelwall Viaduct structures in a £27m scheme.
- A 24/7 contraflow with a 40mph limit starts between junction 20 (Lymm) and junction 21 (Woolston) on 12 October.
- The northbound carriageway closes fully overnight on Sunday 11 October so the contraflow can be installed.
- Northbound joints come first, until spring 2027. The southbound side follows, with completion due in winter 2027/28.
What the Thelwall Viaduct works mean for M6 drivers
The viaduct carries the M6 across the Manchester Ship Canal and the River Mersey, on two separate structures, one northbound and one southbound. More than 180,000 vehicles cross it every day. The scheme began on 1 September with enabling works underneath the viaduct at Warrington Road. Full overnight closures to install traffic management followed between 28 September and 1 October.
The job itself is joint replacement. A bridge deck is never quite still. It expands and contracts as the temperature changes, and it shifts as loads cross it and as the wind pushes against it. Expansion joints allow that movement while keeping a continuous running surface for traffic. National Highways says Thelwall’s joints have reached the end of their operational lifespan, and that replacing them is essential to keep the bridge working safely, reduce the risk of unexpected closures and minimise disruption for road users.
There is one more full closure to get through first. The whole northbound carriageway shuts overnight on Sunday 11 October so the contraflow can be installed. Then, from Monday 12 October, the 24/7 contraflow runs from just after junction 20 to junction 21 northbound, and from just before junction 21 to before junction 20 southbound. A National Highways spokesman described the contraflow as “the safest way to carry out work” while keeping disruption low and significantly reducing the number of motorway closures.
Lane capacity is mostly protected. During the day, northbound drivers will have four lanes: three on the northbound carriageway and one running on the southbound side. Southbound drivers keep four lanes on their own carriageway. At night, the northbound side drops to one lane between 10pm and 5am, although the northbound exit slip road at junction 21 stays open throughout. The 40mph limit and narrow lanes stay in place for the duration of each phase, enforced by average speed cameras.
The work comes in two halves. The first contraflow phase covers the northbound joints and runs until spring 2027. After that, the layout switches. A southbound contraflow goes in, the southbound joints are replaced, and the contraflow is then removed. National Highways expects the whole project to be finished by winter 2027/28.
The scheme is part of the third Road Investment Strategy (RIS3), which covers 2026 to 2031 and includes £8.4bn for resurfacing carriageways and renewing bridges. For more on how bridge work over the canal turns a live motorway into a site, see our August report on the M6 bridge job over the Manchester Ship Canal.
For drivers, the practical change is simple: expect 40mph, narrower lanes and a contraflow between junctions 20 and 21 for more than a year. If you travel through at night, expect one lane northbound. And if you’re travelling on the night of 11 October, check the diversion before you set off.
In this story National Highways