Walter’s Walkway lifted back over the Derwent by 470-tonne crane

Walter’s Walkway has been lifted back over the Derwent in Derby by a 470-tonne crane, four months ahead of schedule, reconnecting Darley Village and Darley Abbey Mills before a mid-November reopening.

Contractor Cawarden has lifted Walter’s Walkway back into place over the Derwent using a 470-tonne crane, four months ahead of schedule.
Derby City Council says the walkway should reopen to the public in mid-November, once new ramps are installed and safety checks are complete.
In brief:
- The prefabricated bridge closed in December 2025 because of safety concerns with the 1930s bridge structure below it.
- In July 2026, the walkway was lifted out of the river entirely so the original bridge could be demolished.
- The East Midlands Combined County Authority (EMCCA) helped fund the urgent demolition work.
How Walter’s Walkway went back in
With the original structure gone, the riverbank was reinforced: new sheet piles were installed and the space behind them filled in. New concrete abutments now give the walkway its foundation.
The demolition and the reinstatement of the walkway had been due to finish by February 2027. The council says it acted quickly, with EMCCA’s support, to get the work done well ahead of that.
Councillor Carmel Swan, Cabinet Member for Climate Change, Transport and Sustainability and a Darley Ward councillor, attended the lift. She said: “This is a huge moment for Darley. The communities at the Mills and in the Village have been cut off for several months and I’m delighted that the bridge is now in place.”
Mayor of the East Midlands Claire Ward said: “We’ve helped fund the urgent work to get the walkway back in place, as well as supporting plans for a new permanent bridge.”
The walkway is a stopgap. The original bridge has been closed over safety concerns since May 2022, and a strategic outline business case published in February identified a new structure offering full-time access for active travel and emergency access for motor vehicles. Cllr Swan said that with the walkway back, the council can now focus on delivering a new permanent bridge for Darley Abbey.
The council hasn’t given the cost of the works or the size of EMCCA’s contribution. Elsewhere, National Highways decided to replace a Salisbury footbridge instead of removing it.
Source: Derby City Council, published 22 October 2026