Wimblington Road closure: £780,000 Manea rebuild dates set

Cambridgeshire County Council has set dates for the Wimblington Road closure in Manea, a £780,000 reconstruction split either side of Christmas, and says diversion routes will be inspected again before work starts.

Wimblington Road in Manea is to be reconstructed at a cost of £780,000, with work due to start on 9 November.
But the question in the village is less about the road being rebuilt than about the roads that will carry its traffic while it’s closed.
In brief:
- The road is due to close from 9 November to 11 December, reopen for the Christmas period, then close again from 5 January to 29 January 2027.
- The diversion runs along Fifty Road, Padgetts Road and Sixteen Foot Bank, which the council says have been inspected and will be re-inspected before work starts.
- Councillor Charlie Marks says residents support the repairs but want assurance that the diversion routes can take the extra traffic.
Wimblington Road closure: what the council has committed to
A Cambridgeshire County Council spokesperson said: “We have committed £780,000 to reconstructing Wimblington Road, Manea, with funding from our Highways Maintenance programme.”
Reconstruction is a bigger job than patching. Patching repairs individual defects and leaves the rest of the road as it is. Under the council’s large-scale maintenance programme, schemes like this involve full reconstruction of the road’s top layers to give a stable surface, with drainage, signage, road markings or vegetation clearance included where needed. The council’s 2025 programme listed this stretch of the B1093, from Boots Bridge, for carriageway recycling. Recycling breaks up the existing road material and reuses it in place as the new structure, so most of the old road doesn’t have to be dug out and carted away. Only emergency vehicles and works traffic will be allowed through during the closure.
The council’s statement followed an open letter from Charlie Marks, a Fenland District and Manea Parish councillor, who asked for clarification on behalf of residents and businesses. He described the repairs as “long overdue” and said residents widely support them. Their questions were whether the work would start on time, whether the road would be rebuilt rather than patched, and whether the closure period was fixed.
His main concern was the condition of the surrounding roads. Cllr Marks highlighted collapsed edges, crumbling surfaces and worsening potholes on Byall Fen Road, Wisbech Road and Fifty Road. Residents also fear winter weather could damage the diversion routes, and want to know whether extra gritting and snow clearance will be provided. He has invited project officers to visit Manea and discuss the concerns with parish councillors.
The council’s reply addresses the diversion directly. It says Fifty Road, Padgetts Road and Sixteen Foot Bank have been inspected for defects and will be re-inspected before the works start next month. Wisbech Road, which it describes as an alternative some drivers might choose, has also been inspected, and repairs there will be carried out before Wimblington Road closes.
That’s the part of highway maintenance residents rarely see written down. A closure moves traffic and load onto neighbouring roads, so the authority has to check those roads first. On fen roads that are already struggling, that check matters. Elsewhere in the county, repair methods are being tested on a peat road in March, as we reported in our piece on the seven methods in its peat road repair trial
In this story Cambridgeshire County Council