Winterstoke Road bridge delayed to 2028 by summer heat

The Winterstoke Road bridge in Weston-super-Mare will now open in early 2028, at least five months late, after summer heat halted piling beside the railway line it crosses.

The replacement Winterstoke Road bridge in Weston-super-Mare will not open until early 2028.
North Somerset Council had been aiming for summer 2027, but piling work beside the railway had to stop repeatedly during this summer’s heat.
In brief:
- The replacement bridge was due to open in summer 2027. North Somerset Council now expects it to open in early 2028.
- Piling beside the Bristol–Taunton railway had to stop during periods of high rail temperatures because of the possible effect on track stability.
- The Ministry of Defence owns the old bridge and is funding the replacement. North Somerset Council will take on the new structure once it’s built.
Why heat stopped the Winterstoke Road bridge piling
The bridge carries Winterstoke Road over the main line between Bristol and Taunton. The original Second World War-era structure had significant structural problems and was demolished over Christmas 2025. Without a replacement, the council says, the route would have had to close permanently. Before it shut, around 20,000 vehicles a day used it.
The new bridge stands on 24 piles, each 35 metres deep and 1.2 metres across, which the council says are needed because of poor ground conditions. The piles sit right next to the operational railway, and that is where the programme came unstuck.
Steel rails expand as they heat up. Because the track is held in place, that expansion builds up pressure in the rails. Network Rail sets temperature limits beyond which work near the line has to stop. Installing deep piles beside the track disturbs the ground the track depends on, so on the hottest days the piling had to halt. The council describes these as preventative safety measures, designed to stop the railway from ever reaching an unsafe condition.
The foundations have to be finished before the bridge itself can be built, so every lost piling day pushes back everything after it. Under the revised programme, the foundation works run until early 2027, the bridge is built during 2027, and the road is completed and opened in early 2028.
“I’m sorry that people will have to wait longer for this route to reopen,” said Cllr Mike Bell, leader of North Somerset Council. “We know the closure is affecting journeys, and residents deserve a clear explanation of the delay and what happens next.” The council and its contractor, Octavius Infrastructure, say they are exploring all available options to bring the date forward.
The Ministry of Defence still owns the old bridge and is funding the replacement, despite the crossing having no military use today. North Somerset Council has agreed to take ownership of the new bridge once it’s complete and to maintain it across a planned 120-year life.
The announcement doesn’t say whether the delay will increase the cost of the scheme, or who would pay if it does. Weston’s roads have featured here recently, when a resurfaced road sparked fresh rat-run concerns.
For drivers, the practical message is another winter and most of another year of diversions. For bridge builders working next to live railways, the lesson is that a hot summer is now a real programme risk.