Wivern Road resurfacing shuts Hull road in two phases from 2 November

Wivern Road resurfacing in Hull starts on Monday 2 November, with Hull City Council rebuilding the deteriorating concrete carriageway in two phases of closures, due to finish by Friday 27 November.

Hull City Council will close parts of Wivern Road for four weeks from Monday 2 November to repair and resurface a concrete carriageway it says is showing signs of deterioration.
The work is planned to be completed by Friday 27 November 2026, weather permitting.
In brief:
- Phase one, Monday 2 November to Tuesday 17 November: the road is closed from No. 8 to No. 12, with access from the south at Amethyst Road.
- Phase two, Wednesday 18 November to Friday 27 November: the road is closed from No. 177 to the junction with Triton Road, with access from the north.
- PBS Construction Limited is carrying out the scheme for the council, between 8am and 5pm, Monday to Friday.
What the Wivern Road resurfacing involves
The council says the works will reconstruct and resurface the road, replace kerbs and footpath crossings, and repaint the road markings. The aim is a safe, even surface for all road users, with improved grip and skid resistance.
Concrete roads fail differently from asphalt ones. They’re laid as slabs, and over time the joints between slabs can break down, edges can crack and slabs can rock or settle. Once that happens, a new surface course alone won’t last, because the movement underneath will crack it again. That’s why schemes like this usually involve reconstruction, repairing the concrete before resurfacing, instead of a straightforward overlay.
Pedestrian footpaths will stay open throughout and bin collections will continue as normal. Residents and businesses will get advance notice by letter drop, and information boards will be placed on site. The council says the dates depend on the weather and may change.
Councillor Mark Ieronimo, cabinet portfolio holder for transport and infrastructure at Hull City Council, said: “Wivern Road is showing signs of deterioration, and these works will address those issues, improve the road surface and help prevent more costly repairs being needed in the future.”
He added: “We recognise that roadworks can cause inconvenience. By carrying out the scheme in two phases, we aim to minimise disruption as much as possible.”
The council hasn’t given a cost for the scheme. Hull’s wider road spending was set out in April, when the council approved its highways investment programme.
Source: Hull City Council, published 22 October 2026