Work about to start on next stage of £80m project to relieve congestion on M25 in Essex

The next stage of an £80m scheme to relieve congestion on the M25 in Essex starts this week.
The work is being carried out around the A13 junction of the motorway near Thurrock.
It is part of a major project to increase capacity at the junction and help unlock the multi-billion pound regeneration of the Lower Thames Valley.
The A13 through the junction is being widened from three lanes to four in each direction and the junction itself is being upgraded by adding segregated left turns to and from the M25, and improvements to the other slip roads.
Safety barriers, drainage and lighting are also being upgraded and it is estimated that the project will help to reduce accidents by 18 per cent. Work is scheduled to be completed by summer 2016.
Highways England announced that work on the upgrade would be completed earlier than planned – bringing it forward from autumn next year to the summer – and that this would be achieved by rescheduling the start of roadworks on the M25.
Work will transfer to the M25 with traffic management being installed and construction work starting on Tuesday (November 17).